Warm weather has enabled the Viaduct Rail Park construction to accelerate.
Utility work on Noble Street has been completed. Foundations for pedestrian lighting, stairs, and platforms will follow.
On the elevated viaduct, the remediation of the soil and metal structures is complete. Bridges have been repainted. The damaged girder over Callowhill Street was replaced in mid-June.
The contractor is well along the way to installing all the support structures on the
|
|
edges of the viaduct that will enable the surface area to be expanded with boardwalks and viewing platforms
The team is anticipating sealing the bridge surfaces with concrete by mid-July. Once the concrete pour has cured, the contractor will install structural bases for the swings, lights and benches. Waterproofing of the slab will also occur after the pour but prior to the landscape installation. By the end of the summer, the team will be preparing for landscape installation and many of the final finishes. |
|